Text of MO SB 10 (2025)
Modifies termination dates of certain sections
Legislative text is a public record. Where LegiScan supplied it, the CC BY 4.0 credit applies.
Source: LegiScan. Bill data and text from LegiScan (legiscan.com), licensed CC BY 4.0 and used in modified form. LegiScan does not endorse the Trans Data Initiative. License: CC BY 4.0(opens another site). Source page(opens another site)
As introduced
22,233 characters
EXPLANATION-Matter enclosed in bold-faced brackets [thus] in this bill is not enacted
and is intended to be omitted in the law.
FIRST REGULAR SESSION
SENATE BILL NO. 10
103RD GENERAL ASSEMBLY
INTRODUCED BY SENATOR HOUGH.
0303S.01I
KRISTINA MARTIN, Secretary
AN ACT
To repeal section 67.5060, RSMo, and to enact in lieu thereof one new section relating to
construction regulation.
Be it enacted by the General Assembly of the State of Missouri, as follows:
Section A. Section 67.5060, RSMo, is repealed and one new
1
section enacted in lieu thereof, to be known as section 67.5060,
2
to read as follows:
3
67.5060. 1. As used in this section, the following
1
terms mean:
2
(1) "Design-build", a project delivery method subject
3
to a three-stage qualifications-based selection for which
4
the design and construction services are furnished under one
5
contract;
6
(2) "Design-build contract", a contract which is
7
subject to a three-stage qualifications-based selection
8
process similar to that described in sections 8.285 to 8.291
9
between a political subdivision and a design-builder to
10
furnish the architectural, engineering, and related design
11
services and the labor, materials, supplies, equipment, and
12
other construction services required for a design-build
13
project;
14
(3) "Design-build project", the design, construction,
15
alteration, addition, remodeling, or improvement of any
16
buildings or facilities under contract with a political
17
SB 10
2
subdivision. Such design-build projects include, but are
18
not limited to:
19
(a) Civil works projects, such as roads, streets,
20
bridges, utilities, airport runways and taxiways, storm
21
drainage and flood control projects, or transit projects; and
22
(b) Noncivil works projects, such as buildings, site
23
improvements, and other structures, habitable or not,
24
commonly designed by architects in excess of seven million
25
dollars;
26
(4) "Design-builder", any individual, partnership,
27
joint venture, or corporation subject to a qualification-
28
based selection that offers to provide or provides design
29
services and general contracting services through a design-
30
build contract in which services within the scope of the
31
practice of professional architecture or engineering are
32
performed respectively by a licensed architect or licensed
33
engineer and in which services within the scope of general
34
contracting are performed by a general contractor or other
35
legal entity that furnishes architecture or engineering
36
services and construction services either directly or
37
through subcontracts or joint ventures;
38
(5) "Design criteria consultant", a person,
39
corporation, partnership, or other legal entity duly
40
licensed and authorized to practice architecture or
41
professional engineering in this state under chapter 327 who
42
is employed by or contracted by the political subdivision to
43
assist the political subdivision in the development of
44
project design criteria, requests for proposals, evaluation
45
of proposals, the evaluation of the construction under a
46
design-build contract to determine adherence to the design
47
criteria, and any additional services requested by the
48
political [subdivisions] subdivision to represent its
49
SB 10
3
interests in relation to a project. The design criteria
50
consultant may not submit a proposal or furnish design or
51
construction services for the design-build contract for
52
which its services were sought;
53
(6) "Design criteria package", performance-oriented
54
program, scope, and specifications for the design-build
55
project sufficient to permit a design-builder to prepare a
56
response to a political subdivision's request for proposals
57
for a design-build project, which may include capacity,
58
durability, standards, ingress and egress requirements,
59
performance requirements, description of the site, surveys,
60
soil and environmental information concerning the site,
61
interior space requirements, material quality standards,
62
design and construction schedules, site development
63
requirements, provisions for utilities, storm water
64
retention and disposal, parking requirements, applicable
65
governmental code requirements, preliminary designs for the
66
project or portions thereof, and other criteria for the
67
intended use of the project;
68
(7) "Design professional services", services that are:
69
(a) Within the practice of architecture as defined in
70
section 327.091, or within the practice of professional
71
engineering as defined in section 327.181; or
72
(b) Performed by a licensed or authorized architect or
73
professional engineer in connection with the architect's or
74
professional engineer's employment or practice;
75
(8) "Proposal", an offer in response to a request for
76
proposals by a design-builder to enter into a design-build
77
contract for a design-build project under this section;
78
(9) "Request for proposal", the document by which the
79
political subdivision solicits proposals for a design-build
80
contract;
81
SB 10
4
(10) "Stipend", an amount paid to the unsuccessful but
82
responsive, short-listed design-builders to defray the cost
83
of participating in phase II of the selection process
84
described in this section.
85
2. In using a design-build contract, the political
86
subdivision shall determine the scope and level of detail
87
required to permit qualified persons to submit proposals in
88
accordance with the request for proposals given the nature
89
of the project.
90
3. A design criteria consultant shall be employed or
91
retained by the political subdivision to assist in
92
preparation of the design criteria package and request for
93
proposal, perform periodic site visits to observe adherence
94
to the design criteria, prepare progress reports, review and
95
approve progress and final pay applications of the design-
96
builder, review shop drawings and submissions, provide input
97
in disputes, help interpret the construction documents,
98
perform inspections upon substantial and final completion,
99
assist in warranty inspections, and provide any other
100
professional service assisting with the project
101
administration. The design criteria consultant may also
102
evaluate construction as to the adherence of the design
103
criteria. The consultant shall be selected and its contract
104
negotiated in compliance with sections 8.285 to 8.291 unless
105
the consultant is a direct employee of the political
106
subdivision.
107
4. The political subdivision shall publicly disclose
108
at a regular meeting its intent to utilize the design-build
109
method and its project design criteria at least one week
110
prior to publishing the request for proposals. Notice of
111
requests for proposals shall be advertised by publication in
112
a newspaper of general circulation published in the county
113
SB 10
5
where the political subdivision is located once a week for
114
two consecutive weeks prior to opening the proposals, or by
115
a virtual notice procedure that notifies interested parties
116
for at least twenty various purchases, design contracts,
117
construction contracts, or other contracts each year for the
118
political subdivision. The political subdivision shall
119
publish a notice of a request for proposal with a
120
description of the project, the procedures for submission,
121
and the selection criteria to be used.
122
5. The political subdivision shall establish in the
123
request for proposal a time, place, and other specific
124
instructions for the receipt of proposals. Proposals not
125
submitted in strict accordance with the instructions shall
126
be subject to rejection.
127
6. A request for proposal shall be prepared for each
128
design-build contract containing at minimum the following
129
elements:
130
(1) The procedures to be followed for submitting
131
proposals, the criteria for evaluating proposals and their
132
relative weight, and the procedures for making awards;
133
(2) The proposed terms and conditions for the design-
134
build contract, if available;
135
(3) The design criteria package;
136
(4) A description of the drawings, specifications, or
137
other information to be submitted with the proposal, with
138
guidance as to the form and level of completeness of the
139
drawings, specifications, or other information that will be
140
acceptable;
141
(5) A schedule for planned commencement and completion
142
of the design-build contract, if any;
143
(6) Budget limits for the design-build contract, if
144
any;
145
SB 10
6
(7) Requirements including any available ratings for
146
performance bonds, payment bonds, and insurance, if any;
147
(8) The amount of the stipend which will be available;
148
and
149
(9) Any other information that the political
150
subdivision in its discretion chooses to supply including,
151
but not limited to, surveys, soil reports, drawings of
152
existing structures, environmental studies, photographs,
153
references to public records, or affirmative action and
154
minority business enterprise requirements consistent with
155
state and federal law.
156
7. The political subdivision shall solicit proposals
157
in a three-stage process. Phase I shall be the solicitation
158
of qualifications of the design-build team. Phase II shall
159
be the solicitation of a technical proposal including
160
conceptual design for the project. Phase III shall be the
161
proposal of the construction cost.
162
8. The political subdivision shall review the
163
submissions of the proposals and assign points to each
164
proposal in accordance with this section and as set out in
165
the instructions of the request for proposal.
166
9. Phase I shall require all design-builders to submit
167
a statement of qualification that shall include, but not be
168
limited to:
169
(1) Demonstrated ability to perform projects
170
comparable in design, scope, and complexity;
171
(2) References of owners for whom design-build
172
projects, construction projects, or design projects have
173
been performed;
174
(3) Qualifications of personnel who will manage the
175
design and construction aspects of the project; and
176
SB 10
7
(4) The names and qualifications of the primary design
177
consultants and the primary trade contractors with whom the
178
design-builder proposes to subcontract or joint venture.
179
The design-builder [may] shall not replace an identified
180
contractor, subcontractor, design consultant, or
181
subconsultant without the written approval of the political
182
subdivision.
183
10. The political subdivision shall evaluate the
184
qualifications of all the design-builders who submitted
185
proposals in accordance with the instructions of the request
186
for proposal. Architectural and engineering services on the
187
project shall be evaluated in accordance with the
188
requirements of sections 8.285 and 8.291. Qualified design-
189
builders selected by the evaluation team may proceed to
190
phase II of the selection process. Design-builders lacking
191
the necessary qualifications to perform the work shall be
192
disqualified and shall not proceed to phase II of the
193
process. This process of short listing shall narrow the
194
number of qualified design-builders to not more than five
195
nor fewer than two. Under no circumstances shall price or
196
fees be a part of the prequalification criteria. Design-
197
builders may be interviewed in either phase I or phase II of
198
the process. Points assigned in phase I of the evaluation
199
process shall not carry forward to phase II of the process.
200
All qualified design-builders shall be ranked on points
201
given in phases II and III only.
202
11. The political subdivision shall have discretion to
203
disqualify any design-builder who, in the political
204
subdivision's opinion, lacks the minimum qualifications
205
required to perform the work.
206
12. Once a sufficient number of no more than five and
207
no fewer than two qualified design-builders have been
208
SB 10
8
selected, the design-builders shall have a specified amount
209
of time in which to assemble phase II and phase III
210
proposals.
211
13. Phase II of the process shall be conducted as
212
follows:
213
(1) The political subdivision shall invite the top
214
qualified design-builders to participate in phase II of the
215
process;
216
(2) A design-builder shall submit its design for the
217
project to the level of detail required in the request for
218
proposal. The design proposal shall demonstrate compliance
219
with the requirements set out in the request for proposal;
220
(3) The ability of the design-builder to meet the
221
schedule for completing a project as specified by the
222
political subdivision may be considered as an element of
223
evaluation in phase II;
224
(4) Up to twenty percent of the points awarded to each
225
design-builder in phase II may be based on each design-
226
builder's qualifications and ability to design, contract,
227
and deliver the project on time and within the budget of the
228
political subdivision;
229
(5) Under no circumstances shall the design proposal
230
contain any reference to the cost of the proposal; and
231
(6) The submitted designs shall be evaluated and
232
assigned points in accordance with the requirements of the
233
request for proposal. Phase II shall account for not less
234
than forty percent of the total point score as specified in
235
the request for proposal.
236
14. Phase III shall be conducted as follows:
237
(1) The phase III proposal shall provide a firm, fixed
238
cost of design and construction. The proposal shall be
239
accompanied by bid security and any other items, such as
240
SB 10
9
statements of minority participation as required by the
241
request for proposal;
242
(2) Cost proposals shall be submitted in accordance
243
with the instructions of the request for proposal. The
244
political subdivision shall reject any proposal that is not
245
submitted on time. Phase III shall account for not less
246
than forty percent of the total point score as specified in
247
the request for proposal;
248
(3) Proposals for phase II and phase III shall be
249
submitted concurrently at the time and place specified in
250
the request for proposal, but in separate envelopes or other
251
means of submission. The phase III cost proposals shall be
252
opened only after the phase II design proposals have been
253
evaluated and assigned points, ranked in order, and posted;
254
(4) Cost proposals shall be opened and read aloud at
255
the time and place specified in the request for proposal.
256
At the same time and place, the evaluation team shall make
257
public its scoring of phase II. Cost proposals shall be
258
evaluated in accordance with the requirements of the request
259
for proposal. In evaluating the cost proposals, the lowest
260
responsive bidder shall be awarded the total number of
261
points assigned to be awarded in phase III. For all other
262
bidders, cost points shall be calculated by reducing the
263
maximum points available in phase III by at least one
264
percent for each percentage point by which the bidder
265
exceeds the lowest bid and the points assigned shall be
266
added to the points assigned for phase II for each design-
267
builder;
268
(5) If the political subdivision determines that it is
269
not in the best interest of the political subdivision to
270
proceed with the project pursuant to the proposal offered by
271
the design-builder with the highest total number of points,
272
SB 10
10
the political subdivision shall reject all proposals. In
273
this event, all qualified and responsive design-builders
274
with lower point totals shall receive a stipend and the
275
responsive design-builder with the highest total number of
276
points shall receive an amount equal to two times the
277
stipend. If the political subdivision decides to award the
278
project, the responsive design-builder with the highest
279
number of points shall be awarded the contract; and
280
(6) If all proposals are rejected, the political
281
subdivision may solicit new proposals using different design
282
criteria, budget constraints, or qualifications.
283
15. As an inducement to qualified design-builders, the
284
political subdivision shall pay a reasonable stipend, the
285
amount of which shall be established in the request for
286
proposal, to each prequalified design-builder whose proposal
287
is responsive but not accepted. Such stipend shall be no
288
less than one-half of one percent of the total project
289
budget. Upon payment of the stipend to any unsuccessful
290
design-builder, the political subdivision shall acquire a
291
nonexclusive right to use the design submitted by the design-
292
builder, and the design-builder shall have no further
293
liability for the use of the design by the political
294
subdivision in any manner. If the design-builder desires to
295
retain all rights and interest in the design proposed, the
296
design-builder shall forfeit the stipend.
297
16. (1) As used in this subsection, "wastewater or
298
water contract" means any design-build contract that
299
involves the provision of engineering and construction
300
services either directly by a party to the contract or
301
through subcontractors retained by a party to the contract
302
for a wastewater or water storage, conveyance, or treatment
303
facility project.
304
SB 10
11
(2) Any political subdivision may enter into a
305
wastewater or water contract for design-build of a
306
wastewater or water project.
307
(3) In disbursing community development block grants
308
under 42 U.S.C. Sections 5301 to 5321, the department of
309
economic development shall not reject wastewater or water
310
projects solely for utilizing wastewater or water contracts.
311
(4) The department of natural resources shall not
312
preclude wastewater or water contracts from consideration
313
for funding provided by the water and wastewater loan fund
314
under section 644.122.
315
(5) A political subdivision planning a wastewater or
316
water design-build project shall retain an engineer duly
317
licensed in this state to assist in preparing any necessary
318
documents and specifications and evaluations of design-build
319
proposals.
320
17. The payment bond requirements of section 107.170
321
shall apply to the design-build project. All persons
322
furnishing design services shall be deemed to be covered by
323
the payment bond the same as any person furnishing labor and
324
materials. The performance bond for the design-builder
325
shall not cover any damages of the type specified to be
326
covered by the professional liability insurance established
327
by the political subdivision in the request for proposals.
328
18. Any person or firm performing architectural,
329
engineering, landscape architecture, or land-surveying
330
services for the design-builder on the design-build project
331
shall be duly licensed or authorized in this state to
332
provide such services as required by chapter 327.
333
19. Any political subdivision engaged in a project
334
under this section which impacts a railroad regulated by the
335
Federal Railroad Administration shall consult with the
336
SB 10
12
affected railroad on required specifications relating to
337
clearance, safety, insurance, and indemnification to be
338
included in the construction documents for such project.
339
20. Under section 327.465, any design-builder that
340
enters into a design-build contract with a political
341
subdivision is exempt from the requirement that such person
342
or entity hold a license or that such corporation hold a
343
certificate of authority if the architectural, engineering,
344
or land-surveying services to be performed under the design-
345
build contract are performed through subcontracts or joint
346
ventures with properly licensed or authorized persons or
347
entities, and not performed by the design-builder or its own
348
employees.
349
21. This section shall not apply to:
350
(1) Any metropolitan sewer district established under
351
Article VI, Section 30(a) of the Constitution of Missouri; or
352
(2) Any special charter city, or any city or county
353
governed by home rule under Article VI, [Section 18]
354
Sections 18(a) to 18(r) or 19 of the Constitution of
355
Missouri that has adopted a design-build process via
356
ordinance, rule, or regulation.
357
[22. The authority to use design-build and design-
358
build contracts provided under this section shall expire
359
September 1, 2026.]
360